Public Sector Roofing Works – Oban
Scope
Single ply roofing overlay to existing structure, including removal of existing rooflights, formation of infill construction, insulation upgrade, and associated detailing works.
Key Challenges
- Live operational environment
- Maintaining watertightness throughout the works
- Exposure to coastal weather conditions
Delivery
Works were delivered as an overlay system to minimise disruption to the building below. Sequencing was carefully managed to maintain a watertight envelope at all times, with daily monitoring and coordination to ensure safe and controlled progress on site.
Outcome
Delivered within programme and within budget.
System successfully passed manufacturer inspection and electronic leak detection.
Completed with no disruption to ongoing operations.
Public Sector Roofing Works – Saltcoats (North Ayrshire Council)
Live re-roofing works delivered within an occupied education environment.
Project Overview
- Approx. 1,800m² of pitched roof area renewed
- Existing building dating to circa 1928
- Live education environment (North Ayrshire Council)
- Multi-roof structure with varying pitches and detailing
Scope
Re-roofing works to multiple pitched roof areas, including:
- Strip and replacement of existing slate coverings
- Installation of new natural slating system (Cupa Heavy 16x10)
- Renewal of battens, underlay, and associated components
- Leadwork to ridges, hips, valleys, and abutments
- Rainwater goods replacement and detailing
Works were delivered in controlled phases to maintain full building operation throughout.
Key Challenges
- Live school environment with restricted working areas
- Maintaining safe segregation between works and occupants
- Complex roof geometry with varying pitches
- Weather exposure impacting sequencing of slating works
- Coordination with client, CA, and ongoing instructions
Delivery
Works were carefully phased and sequenced to maintain safety and control at all times.
Daily site management ensured:
- Safe access and egress routes
- Controlled work zones in line with live environment requirements
- Ongoing quality inspections throughout installation
- Close coordination with the Contract Administrator and Clerk of Works
Material selection and installation methodology were adapted to suit roof pitches and ensure compliance with current standards.
Outcome
- Delivered safely within a live operational environment
- Works completed to required quality standards
- Improved long-term performance and weather resistance of the roof system
- Positive coordination with client representatives throughout